Version 2.0 upgrade
Scheduled Maintenance Report for Jerry's Pool
Completed
The scheduled maintenance has been completed.
Posted Jun 02, 2021 - 08:29 CST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 02, 2021 - 07:59 CST
Scheduled
The Crypto.org chain will be upgraded to version 2.0 at June 1 23:59:00 UTC. The chain will be paused until 33% of all validator nodes have upgraded to the new binary.

I expect that the update will take up to 30 minutes until the mainnet resumes running.
Posted Jun 02, 2021 - 00:52 CST
This scheduled maintenance affected: Nodes (Validator Node, Sentry Node #1, Sentry Node #2), Blockchain (Block Signing Rate), and Cluster Health.